Phillips Road Bridge Timeline
-
Surveys and studies
July-November 2020complete
-
Preliminary designs
September 2020-January 2021complete
-
Final design revisions
January-April 2021in progress
-
Right-of-Way acquisition process
January-June 2021in progress
-
Contractor bids process
May-June 2021subject to change
-
Construction
July-October 2021subject to change
-
Road closure
July-August 2021subject to change