Phillips Road Bridge Timeline

 
  • Surveys and studies

    July-November 2020

    complete

  • Preliminary designs

    September 2020-January 2021

    complete

  • Final design revisions

    January-April 2021

    in progress

  • Right-of-Way acquisition process

    January-June 2021

    in progress

  • Contractor bids process

    May-June 2021

    subject to change

  • Construction

    July-October 2021

    subject to change

  • Road closure

    July-August 2021

    subject to change